Upgraded boiler system saves time and money for Valley Fig Growers.

Valley Fig Growers accounts for almost sixty percent of the California fig industry’s tonnage. When load swings occur, the Miura boilers can be brought on and off line like a light switch to eliminate non-productive steam generation. Scot Kvamme, operations manger, Roy Ziegenfuss, maintenance superintendent and Mike Emigh, president, in front of one Miura boiler. Source: Miura Boiler.
Would $16,000 make you smile? It brought a broad smile to Michael Emigh's face. As president of Valley Fig Growers, a grower-owned marketing cooperative in Fresno, CA, Emigh received the rebate check from Pacific Gas & Electric (PG&E) for the energy efficiency achieved by upgrading Valley Fig's boiler system.

The old system, a 300 BHP firetube boiler, could not be used to its full capacity due to California's strict limitations on the amount of oxides of nitrogen (NOx) that gas-fired boilers can emit. "We would have had plenty of capacity if we could have used the boiler's full potential," says Roy Ziegenfuss, Valley Fig Growers' maintenance superintendent, "but then we would have been in violation of the local smog laws. We had to derate our old boiler down so much that we weren't able to get 300 BHP. We were getting around 175 BHP, which sometimes made it hard for us to maintain proper steam pressure."

In addition to these emissions issues, Valley Fig's 300 BHP firetube boiler took four hours to heat up after shutdown. The unit ran 24 hours a day, five days a week. On the weekend, it was shutdown to allow it time to cool off. Downtime for the boiler may have been good for the equipment but it wasn't so great for the employees. Every Monday morning, one employee had to arrive at work at 2:00 a.m. to start the boiler and have it ready to produce steam by 6:00 a.m.

The inefficiency, both in steam pressure and in time, led Valley Fig Growers to replace its old boiler with two, 100 BHP Miuras. The boilers use the pre-mix method of NOx control. The pre-mix burners combine gas and air in a manifold. They are burned through a flat burner with several little holes in it, which reduces flame temperature and, ultimately, reduces NOx. Reducing the size of the upper and lower headers, eliminating water from the upper header and partially eliminating water from the tubes by having a two-phase mixture of steam and water in the tubes accomplishes a reduction in water volume. This low water content allows for a faster start-up.

"From dead cold, we can have 125 psi of steam in eight to ten minutes," says Ziegenfuss. "If we were to valve off the boiler, it could heat itself up and be to temperature in about five minutes. But we're heating up the boiler and pressurizing our whole plant all at the same time and it still does it in under 10 minutes."

As part of its rebate program, PG&E certified that the boilers achieved the efficiency promised and awarded the $16,000 rebate to Valley Fig Growers. "We've found that we're running more efficiently, our exhaust gases meet the state requirements and, to date, it looks like we're saving eight to ten percent on our gas bills," says Emigh. Perhaps even better yet, no one has to go to work at 2:00 a.m. u

For more information:
Mark Utzinger, Miura Boiler Inc., 847-465-0001
www.miuraboiler.com

Did you enjoy this article? Click here to subscribe to Food Engineering Magazine.

You must login or register in order to post a comment.

Multimedia

Videos

Image Galleries

Plant of the Year 2014

Blue Diamond Growers was chosen as Food Engineering's 2014 Plant of the Year. The Sacramento-based company is the world’s largest producer of almonds and almond ingredients.

Podcasts

Burns & McDonnell project manager RJ Hope and senior project engineer Justin Hamilton discuss the distinctions between Food Safety and Food Defense as well as the implications for food manufacturers of the Food Safety Modernization Act.
More Podcasts

TYSON FOODS

Tyson Foods made headlines announcing the company intends to acquire Hillshire Brands in a deal valued at $8.55 billion. Do you think the acquisition will be beneficial for meat and poultry processors?
View Results Poll Archive

Food Engineering

July 2014

2014 July

The July 2014 issue of Food Engineering features the 12th Annual Replacement Parts Survey. Also covered: OEE improvement steps and increased filtration cycle.

Table Of Contents Subscribe

THE FOOD ENGINEERING STORE

Food-Authentication-Flyer-(.gif
Food Authentication Using Bioorganic Molecules

This text provides critical tools and data needed to augment routine food analysis and enhance food safety by aiding in the detection of counterfeit, and potentially deleterious, foods.

More Products

Clear Seas Research

Clear Seas ResearchWith access to over one million professionals and more than 60 industry-specific publications,Clear Seas Research offers relevant insights from those who know your industry best. Let us customize a market research solution that exceeds your marketing goals.

Food Master

Food Master Cover 2014Food Master 2014 is now available!

Where the buying process begins in the food and beverage manufacturing market. 

Visit www.foodmaster.com to learn more.

STAY CONNECTED

FE recent tweets

facebook_40.pngtwitter_40px.pngyoutube_40px.png linkedin_40px.pngGoogle +